− | ==Stations== | + | ==Stations Kitday== |
− | + | 6? stations in parallel, each having two workspaces: | |
+ | - Bag, Flyer, small flyer, Lanyard (left position, working from left to right. Open bag, grab flyer 1 and 2, put them in bag, grab lanyard, bundle, put in bag, handover to position 2 | ||
+ | - Use scoop to gather: Velcro Loop, Velcro Hoop, LEDs, Motor, Battery. (right postion, working from right to left). Drop in bag. | ||
− | + | Two people working to remove filled kits from the stations and adding supplies. | |
− | + | ||
− | + | Each kit takes 24 seconds to complete, so if we calculate 30 seconds per kit per person, at 4000 kits we need 120.000 manseconds = 33 manhours of labour. Assuming 12 people working and two tending supplies and moving stuff the job will be done in approximately 3 hours. | |
− | + | ||
− | + | ==Stations Badgeday== | |
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− |
Revision as of 11:50, 9 July 2017
Projects:Badge/Sweatshop | |
---|---|
Name | Badge Sweatshop |
StartDate | 2017/07/15 12:00:00 AM |
EndDate | 2017/07/23 10:00:00 PM |
Where | RevSpace, Overgoo 1, 2266 JZ Leidschendam |
Badge Sweatshop
Parts are almost in, we need to assemble badge kits for all our visitors. We are assembling around 4k kits, maybe more, maybe less. To do so, we are organizing a sweatshop for our wonderful volunteers.
Planning
We are planning the sweatshop for the 15th and 16th of July, with the 15th as our main date and we hope not to need the 16th.
We start at 12.00, doors will be open from 11.00. If you're a late arrival we can still use you as a relief for a tired hacker. Please sign up!
We estimate assembling a badge will take approximately 2 minutes (might get faster). With a group of 20 people that comes down to around 8 hours of labour. Yeah, we need your help.
The Sweatshop list
We need your help, please sign up on the list below. We will provide dinner, please let us know in the table below if you have special dietary requirements.
July 15
Name | Allergies/Vega(n)? | Comments |
---|---|---|
Sebastius | - | Will arrive early to set up |
|
|
|
Raboof | driving from Deventer | |
Jelle | ||
Roosted | ||
Dave_o | ||
Kartoffel | Will arrive 10/11-ish | |
Juerd | ||
Polyfloyd | ||
Dany | ||
Stitch | ||
Maeddoc | no | Cyberpanda departs from Amersfoort |
You? | choose |
July 22
Name | Allergies/Vega(n)? | Comments |
---|---|---|
Sebastius | - | Will arrive early to set up |
Anus | Cheezy things | Carying the gold-master firmware |
Kartoffel | ¯\_(ツ)_/¯ | |
raboof | Driving from Deventer | |
You? | choose |
Stations Kitday
6? stations in parallel, each having two workspaces: - Bag, Flyer, small flyer, Lanyard (left position, working from left to right. Open bag, grab flyer 1 and 2, put them in bag, grab lanyard, bundle, put in bag, handover to position 2 - Use scoop to gather: Velcro Loop, Velcro Hoop, LEDs, Motor, Battery. (right postion, working from right to left). Drop in bag.
Two people working to remove filled kits from the stations and adding supplies.
Each kit takes 24 seconds to complete, so if we calculate 30 seconds per kit per person, at 4000 kits we need 120.000 manseconds = 33 manhours of labour. Assuming 12 people working and two tending supplies and moving stuff the job will be done in approximately 3 hours.