Line 40: | Line 40: | ||
* AV tent: 2 | * AV tent: 2 | ||
* NOC tent: 2 | * NOC tent: 2 | ||
+ | |||
+ | * Tickets & Entrance: 4 | ||
+ | * Parking: 4 | ||
+ | * Harbour: 8 | ||
* Deco tent: 2 | * Deco tent: 2 |
Revision as of 09:19, 19 July 2017
TLBakken | |
---|---|
Person Responsible | User:SA007 |
Status | ready |
Budget Required | 300 |
Budget Granted | 300 |
buildup from | 2 aug |
buildup duration | 1 day |
buildup orga | 0 |
buildup angels | 2 |
teardown from | 9 aug |
teardown duration | 6 hours |
teardown orga | 0 |
teardown angels | 4 |
waste | 0 |
comments | Needs to be returned to hack42. |
Colored TL-lights.
There are in total about 200 of these things. 100 are intended for IN tents (can be white, but is not as much fun). The other 100 are for "around the field".
About 20 extension cables have been arranged at the power team. 20 power bricks have been arranged at the shopping team.
orga tents
100 TL's should be distributed to all orga tents
- Stage Pa: 4 (av team)
- Stage No: 4 (av team)
- Stage Re: 2 (av team)
- Bar: 4 (bar team)
- Lounge: 2 (lounge team)
- Silent lounge: 2 (silent lounge team)
- Radio studio: 4
- Speakerdesk: 2
- infodesk front end: 4
- Kitchen: 2
- Angel area: 4
- AV tent: 2
- NOC tent: 2
- Tickets & Entrance: 4
- Parking: 4
- Harbour: 8
- Deco tent: 2
- POC tent: 2
- Porto cabins: 2
- Logistics warehouse: 2
- First aid: 2 (white)
- merchandise: 2
- Stewards: 2
- Security :2
- CTF: 2
- Workshop pi: 4
- Workshop tau: 4
- Lasersea tower: 8
- "arcade" bar: 8
- Family village 1: 3
- Family village 2: 3
- Toilet buildings, where needed; 10
Any others on request.
Terrain
DO check if they are water tight. If not, add transparent tape, this is supplied.
Next to each power box, we can deploy four of them. For this you need an extension cable (see power above) and a power brick (see above). All power stuff has to be wrapped in a garbage bag so it's water tight. Then deployed in a cross form in the range of the power cable.
Like this:
| | ----- ----- | |
Dependencies
- TODO: Other teams needed?
- TODO: Permits required?
- TODO: Power in watts?
- TODO: Network? Private network required?
Status
- TODO: Buildlog...
Howto: Buildup
- TODO: Where to get the stuff from?
- TODO: How many volunteers are required?
- TODO: How much time is required?
- TODO: Provide instructions on how to set up the installation on the event site.
Howto: Teardown
- TODO: Throw/give away?
- TODO: How many volunteers are required?
- TODO: How much time is required?